Construction Application Permit Fees



Following is a list of application fees for Regulation 1102 Construction Permit Applications to the Division of Air Quality.

Permit applications should be mailed to the Division of Air Quality, along with required permit fees. All checks should be made payable to: State of Delaware.

 

Fuel Burning Equipment
Over 10 mmBTU/hr to 100 mmBTU/hr and Crematories $165
Over 100 mmBTU/hr to 150 mmBTU/hr $390
Over 250 mmBTU/hr $1,290
Waste Oil $170
Process Equipment
Maximum Allowable Emissions less than or equal to 10 tons per year per unit $215
Maximum Allowable Emissions greater than 10 tons per year
(+ $2.50 per ton over 10 tons)
$215
Volatile Organic Compound (VOC) Systems
Gasoline Dispensing Facility $120
Bulk Gasoline Terminal Vapor Recovery Unit $265
Storage Vessel, over 2,000 gallons capacity, and containing material with a true vapor pressure of more than 1.0 psia at 100°F.
(This definition shall not apply to storage vessels at Gasoline Dispensing Facilities and Bulk Gasoline Terminals)
$150
Dry Cleaning Facility $265
Waste Water Separator, each $170
Degreaser, open-top, conveyorized $180
Incinerator $490
Other
Water Tank Sandblasting $215
Temporary Emergency Variance $1,000
Variance $5,000
Advertising Fee $325
Amendment(s) to Permits or Variances $175



+