DNREC Permit Tracking Dashboard

The Department of Natural Resources and Environmental Control (DNREC) is committed to providing timely and complete review of all applications for permits and licenses.

As of the Third Quarter, 2018

The Department collects tracking data from DNREC permitting programs, by Division, regarding numbers of applications submitted and the time it takes to process those applications.

These data are for the 12-month period ending on the last day of the reporting quarter (October 1, 2017 through September 30, 2018).

The Department also posts detailed data about some permitting and licensing programs, environmental monitoring, grants and rebates, and more on the Delaware Open Data Portal.

Division of Waste & Hazardous Substances

Applications Submitted Submitted but not Complete Applications Processed Average Days to Process Target Days to Process
Transporters  421 75% 421  25 60
Scrap Tire Facilities  1 100% 9 78.5 60
Recycling  2 100% 2 32.5 60
Composting  3 100% 1  2 60
UST Construction Approval 12 100% 12 10 60
AST Construction Approval 2 100% 2 15 60
Vapor Recovery-Construction 41 85% 41 10 60
Vapor Recovery-Operating 55 45% 47 14 60

Division of Air Quality

Applications Submitted Submitted but not Complete Applications Processed Average Days to Process Target Days to Process
Reg 1102 Minor Source 137 15% 160 100 90
Reg 1102 & 1125 Synthetic Minor 13 23% 17 96 120
Reg 1125 Major Source Pre-Construction 0  n/a n/a n/a 365
Reg 1130 Title V 37 19% 28 401 365

Note: If a Title V permit is not issued prior to the expiration of the existing permit, the terms are extended provided the company applied for the renewal on time.

Division of Water

Under Development.

Division of Watershed Stewardship

Applications Submitted Submitted but not Complete Applications Processed Average Days to Process Target Days to Process
Shoreline/Waterway
– Coastal Construction Letters of Approval 172 0.7% 141 9 10
– Coastal Construction Permits 5 0% 5 66 60
– Mechanical Restoration of the Dune Baseline 7 0% 7 35 40
Sediment/Stormwater
– Plan Review 117 0% 112 45 30

Coastal Zone Act Program

Applications Submitted Submitted but not Complete Applications Processed Average Days to Process Target Days to Process
Coastal Zone Act Status Decision 1 0% 1 10 15
Coastal Zone Act Permit 2 50% 2 10 90

Division of Fish & Wildlife

Applications Submitted Submitted but not Complete Applications Processed Average Days to Process Target Days to Process
Inland Bay Shellfish Aquaculture Leases 22 19 3 184 n/a

Note: Shellfish leases go through a multi-stage process which can involve reviews by other programs within DNREC and always includes time taken by applicants, after preliminary approval, to secure logistical and business resources prior to final review by the department. There is no set target number of days to process, because each application is evaluated on its own merits, and some require longer evaluation, or more communication with the applicant or other sections/agencies.